Condition assessments and design upgrade works to pier
AW Maritime has completed multiple projects at Gellibrand Pier. This has included condition assessment of the pier above and below deck including the coordination of all sub consultants (diving, chloride testing) and detailed design of maintenance works to concrete deck beam and headstock elements and steel and timber piles.
Specific projects completed at Gellibrand Pier have included:
- Condition assessment of piles and timber crossheads
- Rehabilitation works for piles (timber and steel) and crossheads
- Engineering study of gangway tower
- Condition assessment of breasting dolphins (BD2 & BD3)
- Concept design for breasting dolphins (BD2 & BD3)
- Detailed rehabilitation design and construction support to breasting dolphins (BD2 & BD3)